Localising the Provincial Adaptation Plan

Lecture 05 of 7

Costing a localised adaptation action

Putting a defensible cost on a localised adaptation action, using the same discipline a national costing exercise would require.

Video lecture40 minCompletedQuiz passed · 75%Written questions passed · 100%

In this lecture

  • Cost a localised action against a unit-cost reference
  • Include operation and maintenance
  • Present a cost range, not a single figure

Costing what the national plan left blank

0:00Costing what the national plan left blank9:00
Design prototype - the transport is live, but no video file is attached yet.

National adaptation plans frequently cost a priority at a national scale, or not at all. This lecture builds a bottom-up cost for one localised action - a coastal buffer strip for a specific stretch of shoreline - including the maintenance line that most provincial submissions leave out.

A range, honestly bounded, survives review

A single costed figure invites challenge the moment ground conditions differ from the assumption behind it. A cost presented as a bounded range, with the assumptions stated, survives scrutiny because it has already admitted where it could be wrong.

Materials

Yours to keep, and usable away from the platform.

  • Localised costing worksheetWorksheet · 150 KB

Design prototype - the attachments are placeholders and nothing downloads yet.

Quiz passed

You scored 75%. You can take it again at any time - the highest score is the one that counts.

Take it again